Haven't been taking many pictures for awhile because it's hard to tell if we're actually doing anything. We've been done with back fill for awhile and we'ver been working on the under slab sewer piping.
Today we completed the sewer piping. Inspection passed easy peasy no leaks. Kinda sucks because we ordered our under slab insulation a few weeks ago, and we're hoping to have it this weekend so we could start laying the under slab insulation and dropping WWM on it. Have to get our in slab concrete boxes and conduit all squared away in the coming week and have to order the oxy-barrier pex tubing. Should be looking pretty interesting soon!
We also have to select a concrete finishing contractor and we're a bit hung up on that selection. Either way we visited places that one contractor had done and I snapped a shot of hopefully what our finish slab will look like.